Skip to main content

Pool digging

This week excavation started for the pool. Our narrow access, less than 1.2m, required a small excavator (or digger) and 1.5 days to remove the spoil.

The day started at 7am Thursday with the pool being marked out with string lines. We had to be there to set the level of the pool. We're planning a paved area between the pool and house, hence the finished level of the pool coping was set to be 10mm about our verandah. This allows for a gradual slope towards the house, with a strip drain along the house wall.

Setting out the pool also identified that the house is not parallel to the side fence, so we had to decide which one the pool would be parallel to.  We decided the house, so that the paving would also be "square" to the house, ensuring it would be cheaper to lay and a more professional look.

The excavator was a tight squeeze. Removing the gate from its hinges helped, and to get past the wall-mounted gas hot water heater a board was placed on the ground to tilt the machine sideways so it could squeeze past.



Motorised wheelbarrows were used to remove the spoil to the driveway, from where a bobcat was used to transfer it to a dump truck.




In our sandy soil, at first the excavator was having to wait for the two wheelbarrows to be ready. However, as the dig progressed, the deeper clayey sands slowed down the digging and the barrows were soon waiting for the digger.




With the excavation so close to the house, at the end of the dig the excavator was taken out through our gate on the other side of the house.  This was a much longer path but turned out to be quite easy despite numerous obstacles along the way, and some skilful driving.

The bottom of the excavation was then covered with screenings for drainage to a sump at the deep end of the pool.

Structural ply was put in place to stop minor slippages, and reduce the risk to people walking around the top of the excavation.

With small children in our family, a dog and friends visiting, a safety fence was essential.

At the end of 1.5 days we had a hole.









Comments

Popular posts from this blog

Walk-in pantry: advice for designing yours

Now we've been in our renovated home for a week, we've picked up on some minor issues that anyone considering a walk-in pantry or butlers pantry may want to consider. I think we got ours right, and the minor issues are ones we'll correct ourselves, shortly, at low cost.

 Our pantry is exactly that on most days - a pantry. There's no sink, no oven or hot plates, and no exhaust fan. It does have a microwave and a milkshake maker, storage for irregularly used appliances, and a bench top that can be worked on. We could fit plumbing for a sink later, but can't see a need right now.

Big cost savings can be made with a walk-in pantry. By having a separate room and door, there's absolutely no need for cupboards and cabinet doors within the pantry. Think of the pantry as a cupboard!  Bench tops can be practical and not showy - you don't need Corian or Caeserstone surfaces. A walk-in pantry is a separate room, so soft-close drawers to keep noise down aren't …

Review: Bag2Bed - the comfiest bean bag there is?

About a month ago, at the Better Homes and Gardens show in Melbourne, we impulsively splashed out on not one, but three, bean bags.  And not just any - three super large ones from Bag2Bed. As our daughter noted, we now have six bean bags, with three being small children sized ones and three large ones, for a family of four.

At the show, we took two conventional large outdoor beanbags immediately and placed an order for the third - the Queen Size Bag2Bed. Within two weeks we received a call and made arrangements to collect the bag from their factory, which is conveniently close to us in Cheltenham, Melbourne.

The Bag2Bed concept is that instead of a bean bag filled with polystyrene balls, the Bag2Bed is filled with a foam mattress rolled into a ball.  The bean bag cover can be easily slipped off, and the filling unfurls into a mattress.  In our case it is a queen size mattress.

It is easily the most comfortable bean bag we've used, with a firm foam filling.  We 'fight' for …

Monkey bars!

A few months back we picked up a discounted set of monkey bars (aka horizontal ladders) from Bunnings.  They were reduced from $299 to $80 because the packaging was damaged and the bolts for attaching the bars to wooden posts were missing. There were about four sets of bars on sale.

Last weekend I started assembling them myself, using about an extra $175 worth of materials (bolts, washers, nuts, four cypress pine posts, quick set concrete).  When it came to erecting them I needed a helping hand, which I received yesterday.

In the process of working out how and where to assemble them I found that the recommended height is 1.8 - 2.0 metres, and preferably 1.8m.  Soft fall is also important, to a depth of 250-300mm for up to 2.5m around the bars (Playground Equipment Safety Bulletin, February 2011). The Bulletin provides advice about selecting soft fall materials.

We've generally followed this advice, although without soft fall for a little while. The Bulletin identifies the following…